Bug 1972 - Change in ghan date
Summary: Change in ghan date
Status: RESOLVED USER TO VERIFY
Alias: None
Product: IMIS PRODUCTION
Classification: 01.IMIS
Component: IMIS PRODUCTION FORMS AND REPORTS (show other bugs)
Version: unspecified
Hardware: All All
: Normal normal
Assignee: Mahender
URL:
Depends on:
Blocks:
 
Reported: 2019-11-15 18:28 IST by kk
Modified: 2019-11-18 11:01 IST (History)
1 user (show)

See Also:
Database:
Module ID:


Attachments

Note You need to log in before you can comment on or make changes to this bug.
Comment 3 Mahender 2019-11-18 11:01:33 IST
This is done
Comment 1 Mahender 2019-11-18 10:12:35 IST
Dear sir 

As per Yadav ji required approved document by director
Description kk 2019-11-15 18:28:09 IST
Dear Mr Kapur;

Instruction has been received from Management to Change 54 Wk receiving date from 14th Nov to 15th Nov19. Details are in Mr Rakesh Gupta mail (On 15-11-2019 10:59, rakesh.gupta@baba.in wrote:).

Please do needful.

Thanks
-------- Forwarded Message --------
Subject: 	Re: Change the Receiving date of ghan in ERP
Date: 	Fri, 15 Nov 2019 12:54:26 +0530 (IST)
From: 	rakesh.gupta@baba.in
To: 	sk.singh <sk.singh@baba.in>

Respected Sir,
There is no communication gap /error for Ghan receiving date. It is duly confirmed from Mr. Shiv Prasad Ji at our end at the time of receiving ghan. But he convey the message to change the date of some Ghans as per CMD sir direction.

Regards
Rakesh

From: "sk.singh" <sk.singh@baba.in>
To: "rakesh gupta" <rakesh.gupta@baba.in>
Sent: Friday, 15 November, 2019 12:04:42
Subject: Re: Change the Receiving date of ghan in ERP

Why Change in date, Is there any communication Gap/error?? Why date are booked without duly getting confirmed?? Analyze & take proactive approach. Analyze & revert back.
On 15-11-2019 10:59, rakesh.gupta@baba.in wrote:

    R/Sir,


    AS per direction of Shiv Prasad ji, (Dt.15/11/19 10:45:00 AM) we have to change the receiving date of ghan in ERP through IT Dept. as below:-

    Name of item .          Qty.                  Receving Date.          Change Date

    BABA ONE                100  ghan            14/11/19                     No Change

    54 wk                          30 ghan            14/11/19                     15/11/19


    Thanks