Bug 10318 - Required:- GRN cancellation rights
Summary: Required:- GRN cancellation rights
Status: PENDING FOR USER ACTION USER TO VERIFY
Alias: None
Product: IMIS PURCHASE
Classification: 01.IMIS
Component: IMIS PURCHASE FORMS AND REPORTS (show other bugs)
Version: unspecified
Hardware: PC Windows
: Normal normal
Assignee: Mahender
URL:
Depends on:
Blocks:
 
Reported: 2023-03-14 13:28 IST by Shilpa Srivastava
Modified: 2023-03-17 14:06 IST (History)
4 users (show)

See Also:
Database:
Module ID:


Attachments

Note You need to log in before you can comment on or make changes to this bug.
Comment 2 Mahender 2023-03-17 14:06:13 IST
please confirm
Comment 1 Mahender 2023-03-14 14:58:16 IST
"Account and Legal" department please confirm , it is require or not
Description Shilpa Srivastava 2023-03-14 13:28:00 IST
Dear Team,

Kindly create a provision in IMIS regarding cancellation of GRN till the following 
next month on 7th day as GSTR-3B will be filed after 7th of next month. 
The same has already been discussed with Legal Team.

Therefore, we may allow the cancellation of GRN.

So, requesting you to close this issue asap after discussing the same with Legal Team.



Regards,
Shilpa Srivastava
Internal Audit Executive  
Ext. No.-271