Bug 2173

Summary: approval process required if production return the material to store
Product: [01.IMIS] IMIS STORES AND INVENTORY Reporter: dheeraj mani budakoti <dheeraj.mani>
Component: IMIS INVENTORY FORMS AND REPORTSAssignee: Mahender <mahender.singh>
Status: RESOLVED USER ACTION REQD    
Severity: normal CC: sharad.sharma
Priority: Normal    
Version: unspecified   
Hardware: PC   
OS: Linux   
Database: Module ID:

Comment 3 Mahender 2020-08-24 12:59:16 IST
requirement is hold from user side
Comment 2 Mahender 2020-06-22 14:26:18 IST
please call me 9811897870
Comment 1 Mahender 2019-12-05 13:32:59 IST
CALL ME ON 677
Description dheeraj mani budakoti 2019-12-05 11:15:39 IST
Dear Sir,
Still there is no approval process with store if the production return the material to store.Requisition make,approved & issue all process for returned material are done by PRD.